Rail Baltica (Finland)

Finland Rail Baltica

Finland Rail Baltica is an under-construction rail infrastructure project that is intended to integrate the Baltic states in the European rail network. Its purpose is to provide passenger and freight service between participating countries and improve rail connections between Central and Northern Europe, specifically the area southeast of the Baltic Sea. It is also intended as a catalyst for building the economic corridor in Northeastern Europe. The project envisages a continuous rail link from Tallinn (Estonia) to Warsaw (Poland), consisting of links via Riga (Latvia), Kaunas, and Vilnius (Lithuania). Its total length in the Baltic States is 870 kilometres (540 mi), with 213 kilometres (132 mi) in Estonia, 265 kilometres (165 mi) in Latvia, and 392 kilometres (244 mi) in Lithuania. Rail Baltica is one of the priority projects of the European Union (EU). It is part of the North Sea–Baltic Corridor of the Trans-European Transport Networks (TEN-T).

Rail Baltica will add the first large-scale mainline standard gauge railway in the area. Legacy rail networks in Finland, Estonia, Latvia and Lithuania are mainly in Russian gauge (1,520 mm). These countries' first railways were built in the second half of the 19th century while part of the Russian Empire. While some railways were built or converted to narrow or standard gauge between World War I and World War II in the independent or German-occupied Baltic states, these were later converted back to Russian gauge under Soviet occupation rule after 1945.

According to a study produced by Ernst & Young, the measurable socio-economic benefits are estimated at €16.2 billion.: 186  The assessed GDP multiplier effect the Rail Baltica Global Project would create is an additional €2 billion.: 203  As of January 2020, the high-speed railway connection from Tallinn to the Lithuanian-Polish border was expected to be completed by 2026. As of June 2020, the undersea railway tunnel between Tallinn and Helsinki was envisioned to be completed around mid-2026. At the end of April 2021, governments of Estonia and Finland signed a Memorandum of Understanding committing themselves to cooperation in the area of transport. As of February 2023, the tunnel was still at the investigative stage.

Finland Rail Baltica Overview

Finland Rail Baltica Proposed Environmental Impact

Rail Baltica will be an electric railway, motivated by a desire to reduce carbon emissions. The railway has been planned to avoid Natura 2000 protected areas, in addition to minimising impacts on other environmentally sensitive protected areas and existing 1,520 mm gauge railway networking areas. Wherever necessary, noise protection barriers will be installed. Special animal passages will be built through the embankment.

Finland Rail Baltica Stations

The railway project will enable intermodality and multimodality, i.e. transportation of freight through two or more methods of transportation. Rail Baltica includes plans for three multimodal freight terminals located in Muuga Harbour (Estonia), Salaspils (Latvia), and Kaunas (Lithuania). This is intended to create synergies with the existing 1,520 mm railway system infrastructure. There will be seven international passenger stations—in Tallinn, Pärnu, Riga, Riga Airport, Panevežys, Kaunas, and Vilnius—with potential regional stations and connections to airports and seaports.

The section from Helsinki to Tallinn will be operated by existing Scommercial ferries. In the future, a proposed Helsinki to Tallinn Tunnel could provide a rail link between the two cities.

Finland Rail Baltica Parameters

Rail Baltica will be built as a new, publicly owned, fast conventional double-track railway. If the railway runs freight trains, it will be quadruple-track. It will be electrified and equipped with the European Rail Traffic Management System (ERTMS) for Signalling and communications. The maximum design speed is 249 km/h (155 mph) for passenger trains, while the maximum operational speed will be 234 km/h (145 mph). For freight trains, the maximum design speed is 120 km/h (75 mph). The new railway line will be designed with a 1,435 mm (4 ft 8+1⁄2 in) gauge. Other key technical parameters include:
  • The maximum freight train length will be 1,050 m (3,440 ft).
  • The maximum axle load will be 25 tonnes (25 long tons or 28 short tons).
  • No level crossings with roads.
  • No flat crossings with the 1,520 mm (4 ft 11+27⁄32 in) (Russian gauge) rail network.
  • For maintenance and emergency services, access to the main line should be every 2–3 km (1.2–1.9 mi) and in specific areas.
  • The railway will have ballasted track.
  • Its energy system should be 25 kV.
  • Its double track side should be right-hand running.
  • It is ERTMS Level 2, Baseline 3.
  • The network's parameters are in accordance with the EU Technical Specifications for Interoperability (TSI – P2, F1).
The design phase began in 2016, with design activities at the Riga Central Passenger Station and the Riga International Airport passenger station in Latvia to be continued until 2023. Meanwhile, the construction of the Rail Baltica infrastructure started in 2019, the first operations should start on some of the sections by 2028 and the overall corridor should be completed by 2030.

The overall length of the railway between Tallinn and Warsaw will be at least 950 km (590 mi), while the length within the Baltic States proper will be 870 km (540 mi).

Finland Rail Baltica Status

In 2017, all three Baltic parliaments ratified the Inter-Governmental Agreement for the Rail Baltica project, thereby confirming their long-term commitment to the project. In addition, Rail Baltica Global Project's cost-benefit analysis was delivered by Ernst & Young and Atkins International experts, based on the European Union's CBA guidelines. The analysis showed that the project was financially feasible and viable, and its measurable benefits would outweigh the costs.

In August 2016, the spatial planning for the entire Rail Baltica railway line was approved in Latvia by the decision of the Latvian Government. This was followed by the approval of the Lithuanian Government in January 2017 for their respective section from Kaunas to the border with Latvia. The route for the section from Kaunas to the border with Poland, known as Rail Baltica I, is subject to the results of an Upgrade Feasibility Study. On 14 February 2018, the Ministry of Public Administration of the Republic of Estonia approved the spatial plan for the line in Estonia, leading to the setting of the final route and preliminary design of the railway in the country. With Estonia's decision, the spatial territorial planning and preliminary technical design of the Rail Baltica railway in the Baltic States was finalised.

The Rail Baltica project entered the design phase in all three Baltic States with the approval of detailed design guidelines. Certain sections have finished consolidating preliminary technical design, tendering the detailed technical design services, and preparing a BIM strategy. On 20 March 2018, the first Rail Baltica construction design and supervision contract—for Rail Baltica's Riga International Airport railway station, related infrastructure, and viaduct—was signed by Eiropas Dzelzceļa līnijas SIA and PROSIV, the winner of the open international tender and a partnership of suppliers from three countries: Prodex (Slovakia), Sintagma (Italy), and Vektors T (Latvia).

In 2018, studies related to commercialisation and supply materials were finalised, including a long-term business plan, an operational plan, an infrastructure management study, and an upgraded feasibility study of the European gauge railway line from Kaunas to the Lithuanian–Polish border. In 2019, the first cornerstone of Rail Baltica was laid in Estonia to mark the beginning of construction of Saustinõmme viaduct. Also, detailed technical design contracts were signed for the following sections: Tallinn–Rapla and Pärnu–Rapla in Estonia, Kaunas–Ramygala and Ramygala–Latvian/Lithuanian border in Lithuania, and Vangaži–Salaspils–Misa and the main line through Riga in Latvia. With the contracts signed, geotechnical research was started in different sections of the railway in order to gather information about the soil.

In 2020, the development of detailed technical design had progressed to cover 643 km (400 mi) of the main track, which included all railway sections in Estonia and Latvia as well as sections from Kaunas to the Latvian/Lithuanian border in Lithuania.

In Estonia, discussions about environmental impact assessment were started and meetings were planned until the end of 2020. During the discussions, people were invited to ask questions regarding the project's environmental impact, while various technical solutions were presented.

In Latvia, the Riga Central Station construction was officially started with ceremonies on 23 November 2020. On the 3rd of February 2021, the project implementer of Riga Airport Station was also chosen, construction began in May 2021 and is ongoing as of July 2023. Talks with NGOs in Riga were started to discuss technical solutions within the city, especially for infrastructure elements such as crossings and overpasses.

The Russian invasion of Ukraine has raised the importance of this European project, because of the connectivity across Europe that it will create, for civilian and military travel. Lithuania has a new commission to speed construction within the cities (freight terminal facilities and passenger depot). Estonia faces cost increases and construction delays.

As of 2023, the project completion is scheduled for 2030, with a start of services on some of the sections in 2028.

Finland Rail Baltica Project Implementers

The Rail Baltica project is being implemented by the three Baltic States: Estonia, Latvia, and Lithuania. Finland announced in February 2019 that it will also join the project.

The beneficiaries of the Rail Baltica project are ministries of the three Baltic States: Estonia's Ministry of Economic Affairs and Communications, Latvia's Ministry of Transport, and Lithuania's Ministry of Transport and Communications. In 2014, they established RB Rail AS, a joint venture that acts as the main coordinator and project implementer for the project. Its main business is the design, construction, and marketing of the railway. RB Rail AS also submits EU financing proposals for the Rail Baltica purchasing body for all parties for the procurement of studies, plans, designs for the Global Project, sub-systems (control, command, and Signalling and energy/electrification), raw materials, key components, and cross-border track sections.

Rail Baltic Estonia OU in Estonia, Eiropas Dzelzceļa līnijas SIA in Latvia, and Rail Baltica statyba UAB and LtgInfra in Lithuania are the national implementing bodies. All construction carried out by the implementing bodies is done under the supervision of RB Rail AS and is based on common procurement principles, rules, and contract templates.

Finland Rail Baltica Financing

A feasibility study of Rail Baltica in the three Baltic States carried out by AECOM in May 2011 estimated a cost of €3.6 billion for the railway and proved that Rail Baltica is economically viable. Based on that study, key political and practical decisions—both on the national and EU level—were made to implement Rail Baltica.

Since the AECOM study, the project has grown to include additional elements to the Rail Baltica Global Project for better connectivity, passenger mobility, and inter-modality. These additions include routing the Rail Baltica passenger mainline through the Riga International Airport and the construction of the airport passenger station (Latvia), the Kaunas–Vilnius connection (Lithuania), an improved connection in Kaunas (Lithuania), and the construction of the "Ülemiste-Tallinn airport" tram line (Estonia). Moreover, the preparation of environmental impact assessments, spatial planning, and some preliminary designs has provided better investment estimations for the project.

Thus, in April 2017, the overall cost of the Rail Baltica Global Project implementation in all three countries—including the construction of the Kaunas–Vilnius section—was estimated to be €5.8 billion, according to a cost-benefit study carried out by Ernst & Young. According to the analysis, the project's economic feasibility and social benefits were still proved, providing the necessary updated parameters for continued EU and national co-financing of the project.

The project's profitability lies in its wider socio-economic benefits, which Ernst & Young estimated to be around €16.22 billion. In addition, several immeasurable (mostly catalytic) benefits would be created through regional integration, such as tourism development, new business creation, increased attractiveness to FDI, access to new export markets, technological transfer, and innovation.

The project is financed by the member states, the European Union TEN-T budget, and the Structural and Cohesion Funds provided to the EU New Member States. By the start of 2018, the three Baltic States and RB Rail AS had received two grants totaling €765 million designed under the CEF for the construction of the Rail Baltica railway. On 13 July 2018, a third grant agreement was signed for an additional €130 million, of which €110 million was CEF contribution. In July 2020, another CEF funding was received, amounting to €216 million for construction, technical design, and planning works. In total, the project has received around €1.2 billion from the EU and national funds.

In October 2023 Rail Baltica joint venture of the Baltic States, RB Rail AS, announced the signing of an additional cross-border Grant Agreement for Connecting Europe Facility (CEF) funding, which amounted to 928 million euros CEF support. This substantial funding, combined with national co-financing from the three Baltic States, will exceed 1.1 billion euros, enabling necessary activities for further high-speed infrastructure development.

Finland Rail Baltica Rail Baltica Overview

Finland Rail Baltica Locale: Finland, Estonia, Latvia, Lithuania, Poland
Finland Rail Baltica Service Type: Public high-speed railway
Finland Rail Baltica System: Rail Baltica (European gauge railway)
Finland Rail Baltica Services:
Tallinn–Pärnu–Riga–Riga International Airport–Panevėžys–Kaunas/Vilnius–Lithuania/Polish Border
Finland Rail Baltica Planned Opening:
Partial: 2028
Full: 2030
Finland Rail Baltica Number of Tracks: Double track
Finland Rail Baltica Track Gauge: 1,435 mm (4 ft 8+1⁄2 in) standard gauge (primary)
Finland Rail Baltica Electrification: 25 kV 50 Hz AC overhead line
Finland Rail Baltica Operating Speed Passenger: 234 km/h (145 mph)
Finland Rail Baltica Operating Speed Freight:
120 km/h (75 mph)
Finland Rail Baltica Operating Speed Signalling: ERTMS L2

 
Rail Holidays
Rail Vacations
Luxury Trains
Luxury Tours
International Trains
International Tours
www.Rail-Pass.com
                             
home www.Rail-Pass.com Rail-Pass & Train Tickets & International Rail Holidays Hotel Booking & Hotel Reservations & Hotel Accomodation B&B Booking & B&B Reservations & B&B Accommodation Hostel Booking & Youth Hostel Reservations & Hostel Accommodation Chalet Rental & Holiday Homes & Vacation Homes Ski Pass Booking & Ski Pass Reservations & Ski Lift Pass Flight Tickets & Airline Reservations & Flight Booking Ferry Tickets & Ferry Booking & Ferry Reservations Car Rental Booking & Car Hire Reservations Excursions & Days Out & Day Trips & Theme Parks Rail Pass Booking & Rail Pass Reservations & Eurail & Interrail Rail Tickets & Rail Reservations & International Train Tickets Weekend Trips & Weekend Breaks & Weekend Away  Travel Insurance & Business Travel Insurance Eurotunnel Tickets & Eurotunnel Le Shuttle Reservations
Search: