The Charleroi metro was planned in the 1960s as a 52 km (32 mi) network, consisting of eight branch lines radiating from a central downtown loop and no less than 69 stations. If completed as planned, this would have been the largest metro system in the Benelux region.

In the 1960s, Charleroi already had an extensive tramway network, operated by both SNCV and STIC, but trams were starting to be replaced by buses as those were supposedly more flexible, were cheaper to operate and were perceived as more modern. The metro network was meant to offer trams a second life by providing a fast and comfortable mass transit system, while removing them from the street.

Full completion of the initial project was envisioned between 1992 and 1994. As a general rule, plans called for tracks to be at ground level, on dedicated infrastructure (separated from the street). If not possible, priority was given to viaducts, and tunnels were considered as the last option, except in Charleroi downtown or in densely populated areas.

The first section opened on 21 June 1976, between Sud and Villette (which was the first metro station in Belgium to be built on a viaduct). These were served by what would eventually become line 89 of the original light metro system.

Piges and Ouest were opened 4 years later, on 30 June 1980. Each time a new section was inaugurated, trams would transit through it before going back to the street for the remainder of their journey.

Stations Palais, Dampremy, and the section between Morgnies and Paradis were opened on 24 May 1983. Pétria followed on 24 May 1986. The same year, works were completed on a first section of the Châtelet branch (until Centenaire station), however this branch has never been put into service.

The remaining stations on the Anderlues branch (Providence, De Cartier, Moulin and Fontaine) were opened on 22 August 1992. One week later, on 28 August, a first section of the Gilly branch (from the downtown loop until Gilly)) was inaugurated, along with the Waterloo station on the downtown loop. At the time, infrastructure beyond Gilly to Soleilmont was in various stages of completion, but not in service. 54 was created to serve the new branch.

On 30 August 1996, two additional stations were opened on the downtown loop (Janson and Parc). Lines 55 and 88 were created to duplicate the two existing lines while using the northern part of the unfinished loop.

2008 and 2009 saw the resumption of metro construction, following a 75 million euro loan from the European Investment Bank, out of a total estimated cost of 150 million euro. Work to complete the downtown loop started on 20 October 2008, building of the Gosselies branch on 16 March 2009, and the lengthening works on the Gilly branch toward Soleilmont started on 30 March 2009.

The finished downtown loop was put in service on 27 February 2012 with the completion of the Sud to Parc section. The same day saw the opening of the Soleilmont extension of the Gilly branch. The completion of the downtown loop involved a comprehensive reorganization of the lines and the introduction of new numbers (M1, M2 and M4) and colors, and the inauguration of the now "Charleroi Metro".

The Gosselies branch (Line M3) project created a new branch starting at Piges station and running as a regular tramway line toward Gosselies. A large section of the line already existed to the Jumet tram depot, but as it is only used by empty trams going to and from the depot, and was not equipped for commercial passenger transport, it had to be completely rebuilt. The Jumet to Gosselies section is new, although it is built on the site of former SNCV tramway lines.

The project included full renovation of the Chaussée de Bruxelles (Brussels Road) which is used by the new line. Because of the narrowness of some streets in Gosselies, the line uses single track in different streets for each direction.

The Gosselies branch was scheduled for completion in 2011, however multiple obstacles had delayed its opening. The fourth line of the Charleroi Metro thus entered service on 22 June 2013. This northern branch is served by a new line, dubbed "M3" (yellow color), which is how it is now depicted on official maps and on station signage.

Charleroi Trams Overview

Charleroi Trams Owner: Opérateur de transport de Wallonie
Charleroi Trams Locale: Charleroi, Hainaut, Belgium
Charleroi Trams Transit Type: Semi-metro (Light rail)
Charleroi Trams Number of Lines: 4
Charleroi Trams Line Number: M1, M2, M3, M4
Charleroi Trams Number of Stations: 48 (incl. 26 tram stops)
Charleroi Trams Headquarters: Place des Tramways, 9/1 6000 Charleroi
Charleroi Trams Began Operation: 21 June 1976; 48 years ago
Charleroi Trams Operator(s): TEC Charleroi
Charleroi Trams Number of Vehicles: 48
Charleroi Trams System Length: 33 km (21 mi)
Charleroi Trams Track Gauge: 1,000 mm (3 ft 3+3⁄8 in) metre gauge
Charleroi Trams Electrification: 600 V DC overhead

 
Rail Holidays
Rail Vacations
Luxury Trains
Luxury Tours
International Trains
International Tours
www.Rail-Pass.com
                             
home www.Rail-Pass.com Rail-Pass & Train Tickets & International Rail Holidays Hotel Booking & Hotel Reservations & Hotel Accomodation B&B Booking & B&B Reservations & B&B Accommodation Hostel Booking & Youth Hostel Reservations & Hostel Accommodation Chalet Rental & Holiday Homes & Vacation Homes Ski Pass Booking & Ski Pass Reservations & Ski Lift Pass Flight Tickets & Airline Reservations & Flight Booking Ferry Tickets & Ferry Booking & Ferry Reservations Car Rental Booking & Car Hire Reservations Excursions & Days Out & Day Trips & Theme Parks Rail Pass Booking & Rail Pass Reservations & Eurail & Interrail Rail Tickets & Rail Reservations & International Train Tickets Weekend Trips & Weekend Breaks & Weekend Away  Travel Insurance & Business Travel Insurance Eurotunnel Tickets & Eurotunnel Le Shuttle Reservations
Search: